Times Online - Repeated design changes, poor decision making, a now-nationalised yard lacking experience, sub-standard work, government interference and Covid have all been identified as factors in Glen Sannox, earmarked for the Arran crossing, and an unnamed sister vessel being about five years late and costing more than double the original £97 million contract. Despite ministerial assurances, there are doubts that either vessel will ever come into service.