Exactly a year left to complete metro’s civil work
The reverse clock hung on LMRC (Lucknow Metro Rail Corporation)’s premises shows only 364 days left to complete civil work of Lucknow metro. While officials claim around 55% work is already done and hope to meet deadline set by the state government- December 2016, important tenders like underground corridor construction, metro station design near airport, escalators are yet to be finalised. Metro construction had started in September 2014.